Developping an Inherited Scenarios Table

Navigation:  Estimates > Task Sharing >

Developping an Inherited Scenarios Table

Previous pageReturn to chapter overviewNext page

The scenarios are described in Scenarios on WBS Quantities or Other Fields.

The main estimate passes on to child estimates the sub-set of scenarios which applies to them.

If the main bidder has locked certain WBS quantities of the main estimate, the sub-contractor cannot edit them. QDV7 shows a report when the child estimate is fed back into the main one.

A sub-contractor can add its own scenarios. However, they will not change the main scenarios table on feedback.